PROJECT PHASES

Below outlines the anticipated implementation phasing/sequencing plan for the Bradenton Streetscape as of 7/2/2020. The design and construction team have worked together to create a phasing plan that will cause the least amount of impact possible. 

 

 

 

 

 

 

As of 7/2/2020

REWORK PHASE 1 - Tree Lighting Pending

REWORK PHASE 2 - Balance of Site Furnishings and Tree Lighting Pending

REWORK PHASE 3A - COMPLETE

PHASE 3B - Balance of Site Furnishings Pending

PHASE 4 - Tree Lighting Pending

PHASE 5 - December 2019 - January 2020 

PHASE 6 - Tree Lighting Pending

PHASE 7 - June 2020

PHASE 8 - August 2020 

PHASE 9 - March 2020 

PHASE 10 - February 2020 

PHASE 11 - July 2020

PHASE 12 - April 2020 **Changed from Summer 2020

PHASE 13 - September 2020 (Intersections)